News : Missouri's Largest Wind Farm To Begin Construction
Posted by Randy on 2014/1/13 5:46:44 (1130 reads) News by the same author

(newspressnow.com) - Element Power will begin construction on the state’s largest wind farm later this year near Oregon, Mo., in southern Holt County.
Click to see original Image in a new window

The company will generate 200 megawatts of electricity at the Mill Creek Wind Farm and will sell the power to Kansas City Power & Light — representing half of KCP&L’s recent commitment to add 400 megawatts of wind power to its grid.
Scott Zeimetz, project manager for Element Power, said the company spent the past three to four years in the area securing lease agreements with landowners for potential wind turbine sites. The company currently has roughly 25,000 acres under lease with more than 100 landowners.

Although Element Power knows how much electricity it plans to produce, the final number of turbines has not been determined. Mr. Zeimetz said the company likely would choose a commercial model somewhere in the 1.7 megawatt to 2 megawatt range, which would put the number sites needed at 100 or slightly more.

“It all depends on how many turbines we order, and as of yet that hasn’t been decided,” Mr. Zeimetz said.

Construction is expected to begin in the fall. If everything follows according to schedule, the wind farm will begin to operate commercially by the end of December 2015.

The project represents an investment of roughly $400 million in the state of Missouri. About 300 workers will be employed during construction, with 12 to 14 permanent full-time jobs created once Mill Creek becomes operational. Royalties, tax revenue and the general turnover of money in the local economy will provide additional benefits.
“When you’re in a small community like Oregon and Holt County, a project like this can really have an impact,” Mr. Zeimetz said. “Of course, it will be up to the county, school district and whoever else to decide how to spend the revenue.”

Holt County Clerk Kathy Kunkel said the region’s other wind farms provided guidance in how the county would handle tax revenue. Instead of using the “Gentry County model” to provide tax breaks, it would use the more common “Enhanced Enterprise Zone” designation to establish the levels of property tax Element Power will pay.

“That’s really the preferred method by the state because it’s governed by state statute,” Ms. Kunkel said.

Gerald Meadows and Don Scheib, Holt County landowners who have a lease agreements with Element Power, both said they looked forward to the project and its benefits.

“I feel wind is a good source for power production and it offers an additional opportunity to landowners to optimize their land. It provides an excellent opportunity for the county to improve their education system through increased tax revenues,” Mr. Meadows said.

“Anything that will bring in revenue to the county, schools and farmers, in addition to bringing jobs into the county, I’m in favor of,” Mr. Scheib added.
If Mill Creek comes online in late 2015, it will be the first wind farm to begin operation in the region in more than five years.

Six facilities of varying size were constructed starting in 2006, with the most recent one starting operation in 2010.

Wind Capital Group began construction on the state’s first wind farm — Bluegrass Ridge — in 2006 north of King City, Mo. The 27-turbine, 56.7-megawatt facility officially opened in 2007.
Wind Capital brought three more operations online in 2008. The Cow Branch farm consists of 24 turbines that generate 50 megawatts in rural Atchison County. A small four-turbine five megawatt operation called Loess Hills sits on the edge of Rock Port, Mo., between the town’s west boundary and U.S. Interstate 29.

Further east, the company constructed the Conception wind farm, with 24 turbines generating 50 megawatts on the hills surrounding the three communities of Conception, Conception Junction, Mo., and Clyde, Mo., in Nodaway County.
Another company joined the regional wind power industry in 2009, when Iberdola built the Farmers City wind farm near Tarkio, Mo., in Atchison County, with 73 turbines producing 146 megawatts of electricity.

Wind Capital’s latest project, Lost Creek, joined the grid in 2010, with 100 turbines producing 150 megawatts of electricity south and east of King City in Gentry County.

Printer Friendly Page Send this Story to a Friend Create a PDF from the article


Other articles
2015/4/17 11:00:00 - THS Senior Named Missouri's FFA President
2015/4/17 10:31:23 - NCMC Postseason Nemesis To Host National Tournament, Starting in March 2017
2015/4/17 10:30:00 - Trenton Clipped By Chariton In Tight Boys Tennis Battle
2015/4/17 10:21:00 - NCMC Pirates Blow Late-Game Lead, Swept On Thursday
2015/4/17 10:06:32 - Trenton Middle School Boys Win PC Relays
2015/4/17 9:20:00 - Trenton Girls, Brookfield Boys Win Trenton Relays Team Titles
2015/4/17 9:00:42 - Lawson Wins Cameron Golf Invitational, Trenton Sixth
2015/4/17 8:41:25 - Mizzou Basketball Signs Point Guard To '15 Class
2015/4/17 8:20:00 - Phi Mu Epsilon Hosts 90th Anniversary Party At NCMC
2015/4/17 8:10:00 - Daviess County Hosts Solid Waste Collection In May
2015/4/17 8:05:44 - Grand River Tech Organization To Host Mock Accident
2015/4/17 7:57:31 - Sullivan County Lifts Boil Advisory
2015/4/17 7:40:00 - Area FFA Students Compete For State Awards
2015/4/17 7:33:07 - Gallatin Hires New City Administrator
2015/4/17 7:27:41 - Man Shot, Killed In MU Parking Garage
2015/4/16 11:23:07 - NCMC Makes Signing Of THS Standout Official
2015/4/15 15:20:00 - Trenton Girls Dominate TMS Track Meet At CF Russell Stadium
2015/4/15 15:17:18 - Savages Sweep THS Boys Tennis
2015/4/15 15:07:07 - Eighth-Inning Wild Pitch Gives NCMC Baseball Victory In Kansas
2015/4/15 15:00:44 - NCMC Lady Pirates Trample Graceland JV
2015/4/15 13:10:00 - Laredo Board Approves Raise For Certified Staff
2015/4/15 13:10:00 - Newtown-Harris Offers Contract To Principal Foster
2015/4/15 13:10:00 - Princeton Basketball Coach Resigns, Takes Principal Job At Ridgeway
2015/4/15 11:20:00 - Trenton Resident Charged With Marijuana Possession
2015/4/15 11:20:00 - Pleasant View District To Place New Sign In Front Of School
2015/4/15 11:10:00 - Trenton R-9 Announces New Hirings For 2015-16 School Year
2015/4/15 10:40:00 - Novinger Wildcats Cruise At Milan
2015/4/15 9:44:17 - Trenton Lady Bulldogs Win Brookfield Relays
2015/4/15 9:40:00 - NCMC Women's Basketball Hits Iowa For 2015 Recruit
2015/4/15 9:27:25 - Shorthanded Trenton Beats Princeton In Monday Golf Duel



Bookmark this article at these sites

                   

Listen to KTTN-FM