News : Missouri's Largest Wind Farm To Begin Construction
Posted by Randy on 2014/1/13 5:46:44 (868 reads) News by the same author

(newspressnow.com) - Element Power will begin construction on the state’s largest wind farm later this year near Oregon, Mo., in southern Holt County.
Click to see original Image in a new window

The company will generate 200 megawatts of electricity at the Mill Creek Wind Farm and will sell the power to Kansas City Power & Light — representing half of KCP&L’s recent commitment to add 400 megawatts of wind power to its grid.
Scott Zeimetz, project manager for Element Power, said the company spent the past three to four years in the area securing lease agreements with landowners for potential wind turbine sites. The company currently has roughly 25,000 acres under lease with more than 100 landowners.

Although Element Power knows how much electricity it plans to produce, the final number of turbines has not been determined. Mr. Zeimetz said the company likely would choose a commercial model somewhere in the 1.7 megawatt to 2 megawatt range, which would put the number sites needed at 100 or slightly more.

“It all depends on how many turbines we order, and as of yet that hasn’t been decided,” Mr. Zeimetz said.

Construction is expected to begin in the fall. If everything follows according to schedule, the wind farm will begin to operate commercially by the end of December 2015.

The project represents an investment of roughly $400 million in the state of Missouri. About 300 workers will be employed during construction, with 12 to 14 permanent full-time jobs created once Mill Creek becomes operational. Royalties, tax revenue and the general turnover of money in the local economy will provide additional benefits.
“When you’re in a small community like Oregon and Holt County, a project like this can really have an impact,” Mr. Zeimetz said. “Of course, it will be up to the county, school district and whoever else to decide how to spend the revenue.”

Holt County Clerk Kathy Kunkel said the region’s other wind farms provided guidance in how the county would handle tax revenue. Instead of using the “Gentry County model” to provide tax breaks, it would use the more common “Enhanced Enterprise Zone” designation to establish the levels of property tax Element Power will pay.

“That’s really the preferred method by the state because it’s governed by state statute,” Ms. Kunkel said.

Gerald Meadows and Don Scheib, Holt County landowners who have a lease agreements with Element Power, both said they looked forward to the project and its benefits.

“I feel wind is a good source for power production and it offers an additional opportunity to landowners to optimize their land. It provides an excellent opportunity for the county to improve their education system through increased tax revenues,” Mr. Meadows said.

“Anything that will bring in revenue to the county, schools and farmers, in addition to bringing jobs into the county, I’m in favor of,” Mr. Scheib added.
If Mill Creek comes online in late 2015, it will be the first wind farm to begin operation in the region in more than five years.

Six facilities of varying size were constructed starting in 2006, with the most recent one starting operation in 2010.

Wind Capital Group began construction on the state’s first wind farm — Bluegrass Ridge — in 2006 north of King City, Mo. The 27-turbine, 56.7-megawatt facility officially opened in 2007.
Wind Capital brought three more operations online in 2008. The Cow Branch farm consists of 24 turbines that generate 50 megawatts in rural Atchison County. A small four-turbine five megawatt operation called Loess Hills sits on the edge of Rock Port, Mo., between the town’s west boundary and U.S. Interstate 29.

Further east, the company constructed the Conception wind farm, with 24 turbines generating 50 megawatts on the hills surrounding the three communities of Conception, Conception Junction, Mo., and Clyde, Mo., in Nodaway County.
Another company joined the regional wind power industry in 2009, when Iberdola built the Farmers City wind farm near Tarkio, Mo., in Atchison County, with 73 turbines producing 146 megawatts of electricity.

Wind Capital’s latest project, Lost Creek, joined the grid in 2010, with 100 turbines producing 150 megawatts of electricity south and east of King City in Gentry County.

Printer Friendly Page Send this Story to a Friend Create a PDF from the article


Other articles
2014/7/28 5:52:19 - Motorcycle Accident Injures One; Driver Accused Of DWI
2014/7/28 4:43:45 - Missouri Congressional Hopefuls Run On Low Budgets
2014/7/28 4:39:04 - One Killed In Shooting At University City Alumni Picnic
2014/7/28 4:30:00 - First In Line: Woman Waits Days To See President Obama Speak
2014/7/28 4:20:00 - Bar Catches Heat For Sign Insensitive To Women
2014/7/28 4:14:32 - Teen Arrested After Gas Station Clerk Pulls Gun
2014/7/28 4:11:10 - Farmers Brace For High Corn Yields, Lower Prices
2014/7/28 4:05:48 - 4-Year-Old Abducted From Missouri Found In Virginia
2014/7/25 6:26:53 - Motorcycle Accident Injures Cameron Resident Near Mooresville
2014/7/25 4:42:55 - Child Abuse Charges Include Snakes, Lizards And Alligators
2014/7/25 4:40:00 - Search Warrant Leads To Two Meth Suspects
2014/7/25 4:30:00 - 3 Convicted In $17 Million Drug Conspiracy
2014/7/25 4:26:15 - Woman Ticketed After Stopping To Help Stranded Ducklings
2014/7/25 4:22:33 - 10-Month-Old Baby Dead After Being Left In Hot Car
2014/7/25 4:15:23 - Husband Documents Wife's Reasons For Rejecting Sex, Sends To Her Work Email
2014/7/25 4:07:44 - Family Feud Sparks Revolt At Grocery Store Chain
2014/7/25 4:01:28 - Livingston County Sheriff Investigation Report
2014/7/24 11:03:48 - Two Spickard Residents Arrested On Drug Charges
2014/7/24 10:51:09 - Fire Damages Trenton Residence This Morning
2014/7/24 10:50:00 - Inmate At Daviess/DeKalb Jail Charged With Hitting Man 240 Times
2014/7/24 10:10:45 - Highway 65 And 28th Street Topic Of Meeting
2014/7/24 9:59:51 - Two Have Cases Heard In Court At Trenton
2014/7/24 9:56:09 - Caller Posing As Grundy Electric Employee In Attempt To Collect Payment
2014/7/24 9:52:51 - Trenton Resident Arrested
2014/7/24 4:46:07 - Man Caught Snapping Pictures At Pool With Concealed Camera
2014/7/24 4:35:31 - KC Leaders Endorse Ban On Openly Carrying Guns
2014/7/24 4:28:51 - Couple Arrested For Having Sex On Public Beach In Broad Daylight
2014/7/24 4:26:02 - 4-Year-Old Boy Banned From Doughnut Shop
2014/7/24 4:21:38 - Missouri Man Accused Of Leaving Infant Twins Unattended In Car
2014/7/24 4:14:50 - Arizona Execution Takes Nearly Two Hours



Bookmark this article at these sites

                   

Listen to KTTN-FM